HARVARD
CARRIAGE SHED
PHASE
TWO
Once the siding and south addition were removed, we started the rafter and ridgepole removal. As we progressed, we selectively stripped the building of its sheathing. We did this in phases, as the wide sheathing boards were partially responsible for the building's structural integrity. So many post bases and plate ends were rotted or missing that we had to add bracing in a few places; more was added to the rafters themselves.
The ridgepole had some damage near the south end, so we sandwiched the deteriorated area with 2x6.
As rafters were removed, we laid them over the front plates; this allowed for a place to put the 40-foot ridgepole so we could adjust the straps.
Lowering the ridgepole to the ground
Loft floor with raised ceiling under the hogshead barrel. The hogshead had a family of mice we gently displaced and kept doing so until there were no more places for them to go. They eventually leapt from the ceiling to the workroom floor and finally hightailed it to the brush on the last day of demo.
Looking north
Half of the flooring and floor joists removed before one of two rain days
Removing a stubborn hurricane brace by pounding out the trunnel
More trunnel pounding. Some had to be drilled.
Removing the last piece of sheathing. My t-shirt reads "Without Struggle The is No Progress." How true.
Dan and I wrestling timbers onto the lull.
Nothing left but the piles of lumber to be banded. Note the plywood to the right of the piles. It covers the partially-removed workroom floor.
The last bit of demolition gave us another hidden extra as exciting as the 'slaughter table' we found the second week. We had removed one layer of the three (!!!?) that composed the workroom floor, and had seen the end of a very thick chestnut timber holding up the flooring as an improvised joist. As Ken removed the last layers, he hollered at me.
"You're not gonna believe this!" he called. I looked and saw a round hole in the 20" x 20" timber being revealed.
"It's got a hole!" I said. "Wonder what it was for?"
"Like I said, you're not gonna believe it!"
When he pulled the last boards off, he revealed not one but three holes.
And two of them were threaded.
It was a frame for a large press, likely for cider. The remaining 'joists' were other members of the press, and though it was incomplete, it was pretty impressive.
Though chestnut is a comparatively light wood, it took the lull to lift the headframe.
We brought it back and I hope we'll eventually make some of the missing pieces, but who knows? It may be milled into a mantle somewhere. Hopefully the threaded holes will be prominently displayed.
Guiding the forks
Loading the ridgepole; it rode between the stacks in the middle of the trailer
Spider Jim examining the load as it is stacked
Preparing to finish stacking the load, though last time it was loading the stacks.
Last to be loaded; a ton of slate
Thanks God for the lull! Note the straps are being used to lift the slate, even though it's on a pallet. The lull's forks would not tilt.
Fully loaded; note the cider press pieces in the center of the stacks.
Not too high
Nor too wide
After three weeks, only the dumpster remains
Another cool vestige uncovered and a job well done.
ReplyDeleteI really enjoyed this photo record of a hard but meaningful job. Yall even cared about the mice!
ReplyDelete